Safe Routes to School

Project Locations 9-25-2024

Schedule

Advertise: April 22, 2024
Bid Open: May 16, 2024
Project Award: July 16, 2024
Construction Start: October 14, 2024
Anticipated Project End: February 2025

How will this work affect you as a resident or business? 

The work associated with this project will require traffic control and daytime lane closures along Amador Valley Boulevard, Burton Street, Central Parkway, Aspen Street, Hibernia Drive, Grafton Street, and Antone Way.

Parking

While the work is in progress, the City’s contractor may need to prohibit parking on the street. The contractor will post “No Parking” signs a minimum of 72 hours (3 days) in advance of the scheduled work on your street.  Please be aware that, due to the possibility of unforeseen circumstances, such as equipment breakdowns and inclement weather, the posted dates and times could change.  You may continue to park on the street until the date and time shown on the signs.  We appreciate your cooperation in adhering to the temporary “No Parking” restrictions.  If you are planning to be out of town during the time that the work is to take place, please arrange to park your vehicle(s) off of the street to avoid having your vehicle(s) towed.  Emergency vehicles will have access to the streets at all times. 

We apologize in advance for any disruptions caused by this work. Thank you for your cooperation as the City of Dublin invests in improving the pedestrian infrastructure in the City.

This project is made possible by Measure B and Vehicle Registration Fee (VRF) funds, in partnership with Alameda County Transportation Commission.