As of January 13, 2023, the status of the citywide improvements are as follows:
Completed
- Sports fields and courts lighting replacements at
- Dublin Sports Grounds
- Emerald Glen Park (including the skatepark)
- Fallon Sports Park
- Kolb Park
- Solar panel installation at
- Corporation Yard
- Dublin Library
- Fallon Sports Park
- Fire Station 17 & 18
- Heating and air conditioning replacement and/or controls upgrade at
- Dublin Library
- Fire Station 16, 17 & 18
- Heritage Park and Museum
- Senior Center
- Pool control systems firmware upgrade at
- The Wave
- Interior and exterior LED lighting replacement at
- Corporation Yard
- Dublin Library
- Dublin Sports Grounds (exterior)
- Emerald Glen Park
- Fallon Sports Park
- Fire Station 16, 17 & 18
- Kolb Park (exterior)
- Senior Center
- Shannon Community Center
- The Wave
- Park Lighting (non-sports fields and courts lighting) upgrades at
- Alamo Creek Park
- Bray Commons Park
- Emerald Glen Park
- Heritage Park and Museum
- Shannon Park
- Ted Fairfield Park
- Street Lighting at the Dublin Ranch Special District
In Progress
- Solar panel installation at
- The Wave (along with battery energy storage system)
- Senior Center
- Traffic Signal Resiliency (batteries & fuel cells)
- Battery Energy Storage System
- Corporation Yard
- Resiliency (generators) at
- Dublin Library
- Shannon Community Center
- Fire Station 16
Upcoming
- Solar panel installation at
- Civic Center (along with battery energy storage system)
- Dublin Sports Grounds
- Public Safety Complex
- Resiliency (generators) at
- Fire Stations 17 and 18 (replacement)
- Park Lighting (non-sports fields and courts lighting) upgrades at
- Dolan Park
- Mape Memorial Park
- Electric Vehicle Charging at
- Dublin Sports Grounds
- Public Safety Complex (fleet)