San Ramon Road Overlay Project

Project Overview

The City of Dublin contracted with DeSilva Gates Construction, LP, for the construction of improvements on San Ramon Road in Summer 2018.  The project included the following:

  • Installation of a rubberized asphalt overlay on San Ramon Road from I-580 to Alcosta Boulevard
  • Installation of a hot mix asphalt overlay of Amador Valley Boulevard, west from San Ramon Road to the cul-de-sac
  • Installation of a hot mix asphalt overlay of Dublin Boulevard from Hansen Drive to San Ramon Road
  • Repaving of the multi-use pathway along San Ramon Road from Dublin Boulevard to Silvergate Drive and from Shannon Avenue to Alcosta Boulevard (NOTE: Repaving of the path from Silvergate Drive to Shannon Avenue was done in 2017.)
  • Reconstruction of curb ramps
  • Installation of traffic signal video detection systems
  • Adjustment of utilities to finished grade and restriping

Schedule

Construction took place from June 2018 through mid-October 2018.

Questions

If you have any questions about the project, please contact the City of Dublin Public Works Department at 925-833-6630.